INBENCH

 

 

Network - Local Switching

No.

List of measures

Utilisation

2.1.1

% of line card capacity in use of total line card capacity deployed (4kHz/56kbps/64kbps channel equivalents)

%

2.1.2

% of lines connected to local switches capable of supporting ISDN (4kHz/56kbps/64kbps channel equivalents)

%

No.

List of measures

Reliability

2.2.1

Number of local switch faults reported p.a. per 4kHz/56kbit/64kbit channel equivalent in use

#

2.2.2

% of local switch faults reported again within 30 days of first clear (repeat faults)

%

Network Development

No.

List of measures

Labour productivity

Capital productivity (excluding labour costs)

Total Productivity (including labour costs)

2.3.1

Local switch procurement and installation manhours per additional 4kHz/56kbps/64kbps channel equivalent of local switch capacity deployed

H

2.3.2

Line card procurement and installation manhours per additional 4kHz/56kbps/64kbps channel equivalent of line card capacity deployed

H

2.3.3

Local switch equipment cost per additional 4kHz/56kbps/64kbps channel equivalent of local switch capacity deployed

$

2.3.4

Line card equipment cost per additional 4kHz/56kbps/64kbps channel equivalent of line card capacity deployed

$

2.3.5

Total average local switch cost per additional 4kHz/56kbps/64kbps channel equivalent of local switch capacity deployed

$

2.3.6

Total average line card cost per additional 4kHz/56kbps/64kbps channel equivalent of line card capacity deployed

$

Operations & Maintenance

No.

List of measures

Labour productivity

Total Productivity (including labour costs)

2.4.1

Average time from reported to cleared local switch fault

H

2.4.2

Total local switch O&M manhours per 10,000 4kHz/56kbps/64kbps channel equivalents in use

H

2.4.3

Total local switch O&M cost per 4kHz/56kbps/64kbps channel equivalents in use

$

All national averages over the last 12 months

Specify which 12 month period, but give option of defining own if the one given is unsuitable/unable to collect data for it.

Procurement and installation of switches includes costs/manhours associated with the purchasing procedure of the switch, including the switch cost and installation and supervision (if the work is contracted out).

Labour costs and man hours should be direct labour costs and man hours, including those associated with supervision and direct clerical support, but should not include allocated overhead such as management and R&D.

Network - Switching number of measures:

13

Copyright Analysys 1999